Work is underway on the SS225 Della Fontanabuona, which will involve the implementation of an alternating one-way system. This measure will come into force from 08:00 on 5 February 2025 until 17:00 on 14 March 2025.
The section affected by the measure extends between the Carasco Crossroads and the Gattorna Crossroads. All motorists are advised to pay particular attention to signs and to drive carefully in this area to ensure their own safety and that of operators.
Details:
- Road: SS225 Della Fontanabuona
- Type of measure: One-way traffic
- Work start: 5 February 2025, 08:00
- Work end: 14 March 2025, 17:00
- Affected stretch: Between Incrocio Carasco and Incrocio Gattorna
It is recommended to plan your journeys in advance and, if possible, to use alternative routes to avoid congestion and delays.
(source: cciss ; image for illustrative or stock purposes only)